Nearing completion

highway-work

Duane Hicks

Paving on the final section of the King’s Highway project should take place in the latter half of next week. The contractor is awaiting water sample results for the newly-installed watermain. If they come back clear, they’ll complete the final four watermain tie-ins, then install the geogrid, place granular materials at the watermain tie-in locations, and pave the road. The concrete island at the intersection of First Street West and King’s Highway also needs to be poured.