Hallett’s boatload of work able to be split amongst different bidders

By Liam Oliver Neilson

Local Journalism Initiative Reporter

lneilson@fortfrances.com

It’s been determined that the Hallett will be going back into the water after Fort Frances Town Council revisited the topic on Monday evening’s meeting.

The Hallett is an over 18-metre-long tugboat built by the Russell Brothers of Owen Sound that was—at one point—the largest boat on the Rainy Lake. It was used to pull log booms across the lake for the pulp and paper mill until 1974, when trucking was deemed more economically efficient for boom transportation.

Last December, the previous term of council decided to put the boat back in the water and the project was put out for tender. However, the town was looking for a contractor who would be able to cover every task required for the project and received no bidders as a result.

The full scope of the project included repairs to the cribs in the water, painting the hull and hoisting the boat back into the water via crane.

“We had put out a request for proposals for putting it back in the water and doing basically everything from the sandblasting, prep, paint, the rehab work of the cribs and lifting it in, and we received no bids,” said Infrastructure and Growth Manager Travis Rob.

After getting no bids to restore and lift the Hallett, administration was instructed to tender each component of the work separately, in hopes of receiving bids from a mix of contractors who could handle different pieces of the job.

“Council had directed us to split it up into pieces to tender each piece individually,” Rob said. “But that’s a time-intensive thing that came right in the heart of construction season.”

Due to the time this directive came along, many contracting businesses had their hands full with other work for the season and administration was again unable to find anyone to award the tender to.

Now, after the newly-elected council revisited the topic at their first meeting of council on Monday evening, they have opted to return the boat to its crib in the water; once again allowing contractors to bid on separate parts of the job without needing to rely on a single company to handle each component.

“Sometimes the work is too big, too specialized and it limits the bids,” CAO Marcel Michaels said. “We try to get someone to handle them all together, so if you can get a company that bids on all of it, great, that’d be awesome. But if not, at least we can get specific bids and complete the work in pieces if needed.”

The tender package has yet to be rolled out for contractors to view; however, Rob said he is expecting to see the boat back in the water by end of summer, as much of the work is dependent on warm temperature.

“The reality of that is before we can put it back in the water, we’ve got to get someone to redesign the cribs and we’ve got to get someone in there to prep and paint the hull,” he said. “That stuff can’t happen in the wintertime, so that won’t start until spring.”